Case Study Quick Facts:
-
Client: Venture capital firm acquiring bakery manufacturing operations
-
Investment: $40MM automated pie production line purchased pre-acquisition
-
Challenge: Production line was non-operational, with a commitment to supply 25MM pies annually to a major retailer
-
Urgency: Sterling was contacted the week before Thanksgiving; production needed to hit 90% OEE by Q1
-
Assessment Scope: 50,000 sq. ft. process involving 17 OEMs—dough mixing, ovens, nitrogen freezers, x-ray systems, robotics, and palletizing
-
Sterling’s Role: Deployed 3 engineers for 6 weeks to assess process capability, identify gaps, and document corrective actions
-
Outcome: Created a comprehensive technical and financial risk profile. The client decided to abandon pie production. Sterling conducted a follow-up assessment to repurpose the line for core muffin production.
When a venture capital firm acquired a bakery with a newly installed—but non-operational—$40M pie production line, they turned to Sterling Engineering to assess the situation, identify risks, and uncover a path forward.
Sterling Engineering helped a venture capital (VC) client redesign a production line at a pizza manufacturing facility to produce a new product that would be co-manufactured and sold to big-box stores. This VC client later acquired another bakery manufacturing company that had already purchased a new production line to manufacture pies at scale for big box stores. After the acquisition, it was determined that the production line was not operational. The VC asked Sterling to visit the manufacturing facility and conduct a process assessment to determine the gap between the current state of the process and the future state needed to deliver the client’s expected business outcomes.
Project Challenges
- VC Client purchased a bakery company that recently installed a $40 million automated production line and committed to supplying a big-box retailer with 25 million pies annually.
- The production line was commissioned in Q3, and production was required to start running at 90% OEE by the beginning of Q1. The client called Sterling the week before Thanksgiving to assemble the resources to begin the process assessment as soon as possible.
- The process spanned 50,000 square feet and consisted of automated dough mixing and pie-making equipment, conveyor ovens, cooling tunnels, Nitrogen-Freezers, x-ray machines, high-speed robotic tray and case packing, and palletizing equipment from 17 different OEMs.
Results
Sterling Engineering deployed a team of 3 engineers over 6 weeks to conduct the process assessment. The team defined the client’s expected business outcomes, reviewed the entire process (raw material – finished goods), inventoried equipment issues, and identified the corrective actions needed to make the process capable of delivering the client’s expected outcomes.
We developed a risk profile that summarized the technical and financial risks associated with fixing the process within the schedule constraints. After reviewing it with the executive team, pie production was abandoned, and Sterling Engineering was asked to conduct a separate assessment to determine which components of the $40 million production line could be repurposed to expand the production of their core business, which is muffins.